Drywall & Framing: what bids leave out

Drywall and framing bids are usually built from the same wall types, but bidders draw different lines around them. One carries in-wall blocking, acoustic insulation, the specified finish level and ACT ceilings. Another carries studs and board to a lower finish and leaves the rest to someone else. The low bid may not include walls you can actually paint.

Level your drywall bids with this checklist →

Standard scope checklist

Send this to every bidder and ask them to mark each line Included, Excluded or give an Add $. Silence is not inclusion.

#Scope item
1Wall types per drawings: stud gauge, spacing and height
2Deflection track and head-of-wall details
3Fire-rated assemblies per listed designs
4Shaft walls
5In-wall blocking for casework, grab bars, TVs and equipment
6Sound / acoustic insulation in walls
7Thermal insulation at exterior walls
8Drywall type per location (moisture-resistant, abuse-resistant, Type X)
9Finish level per spec (Level 4, Level 5 where noted)
10Corner bead, reveals and trims
11Drywall ceilings and soffits
12Acoustic ceiling tile (ACT) grid and tile
13Access panels: furnished vs. installed
14Installing hollow metal door frames in stud walls
15Firestopping and head-of-wall fire joint systems
16Patching around other trades' work
17Demolition of existing walls and ceilings
18Lifts, scaffolding and access
19Material stocking and hoisting
20Cleanup and debris removal
21Overtime or phased work
22Sales tax, bond and prevailing wage

Common exclusions and how they are worded

ExclusionTypical wordingWhy it mattersTypical cost to cover
Blocking
  • “Excludes blocking”
  • “Blocking by others”
  • “Blocking only where shown”
Every grab bar, cabinet, TV and wall-mounted fixture needs backing inside the wall before it is closed up. It is cheap during framing and expensive afterwards.TBD
Finish level
  • “Level 4 finish throughout”
  • “Excludes Level 5”
  • “Finish to industry standard”
Higher finish levels take more labor. A bid at a lower finish level than specified looks cheaper and may show every flaw under paint and lighting.TBD
Insulation
  • “Excludes sound insulation”
  • “Insulation by others”
Acoustic batts in office and restroom walls are often specified but excluded. Without them, walls don't perform as designed.TBD
Ceilings
  • “Excludes ACT”
  • “Ceilings by others”
  • “Excludes drywall ceilings / soffits”
Ceiling work is sometimes a separate sub. If the drywall bid excludes it, make sure an ACT bid covers all of it.TBD
Rated assemblies & firestopping
  • “Excludes firestopping”
  • “Excludes head-of-wall fire joints”
  • “Rated walls per UL design by others”
Rated walls only work if they're built to the listed design and every joint and penetration is sealed. That has to be someone's scope.TBD
Access panels & frames
  • “Access panels furnished by others”
  • “Excludes setting door frames”
Small items that span trades: someone furnishes panels and frames, and someone sets them in the wall.TBD
Patching after other trades
  • “Excludes patching after MEP”
  • “One mobilization for patching”
Every MEP change after board goes up needs a patch. Ask how many return trips the bid includes.TBD
Demolition
  • “Excludes demolition”
  • “Demo by others”
On a TI, existing walls and ceilings have to come out. Check whether the drywall or demo sub carries it.TBD
Access & schedule
  • “Excludes lifts”
  • “Excludes overtime / phasing”
High walls, ceilings and occupied phasing add equipment and labor. A single-phase, normal-hours bid assumes the easiest version of the job.TBD

“Typical cost to cover” is TBD. We will publish ranges only once we have real, sourced data. Until then, use your own estimate or a confirmed add price from a bidder.

Questions to ask bidders

  1. What finish level did you price, and does it match the spec in each area?
  2. Is in-wall blocking included for all casework, accessories and wall-mounted equipment?
  3. Are sound insulation and exterior wall insulation included?
  4. Are ACT and drywall ceilings included?
  5. Are rated walls built to the listed designs, and are firestopping and head-of-wall joints included?
  6. Who furnishes and installs access panels and door frames?
  7. How many patching mobilizations after MEP are included?
  8. Does your price assume one phase and normal hours?
Placeholder

Bid-ready drywall contractors

Contractors who agree to price against the standard checklist above, with exclusions spelled out line by line. Listings are not live yet.

Featured listing

Your company · City, ST

Bids on the BidGaps checklist

Featured listing

Your company · City, ST

Bids on the BidGaps checklist

List your company →